83b54f12-8ad5-4318-8fbc-0d87e46a07a7 | The Grange Solar | Solar | Announced | | https://grange-solar.com/ | Private | | | | | Russells Point, OH 43348, USA | 43348 | OH | 40.45054565 | -83.89332154 | 2,570 | | 500 | The Grange Solar project is a solar-powered facility located in Logan County, Ohio. It spans approximately 4,100 acres, with about 2,600 acres dedicated to above-ground infrastructure, including solar arrays and related equipment 1, 2.
The facility's expected power output is up to 500 megawatts (MW) with 210 MW recognized by PJM as capacity. The project will utilize ground-mounted photovoltaic solar panels 3, 2.
The project involves a project-level substation, which will include collection line feeders, breakers, an electrical bus, a main power transformer, a high voltage breaker, metering/relaying transformers, disconnect switches, and an enclosure containing power control electronics. This substation will deliver power through a short generation-tie line to a single point of interconnection 2, 2.
The facility's commencement dates indicate that construction is planned to begin in the second quarter of 2026, with commercial operation expected to start in the fourth quarter of 2027 | 24-0801-EL-BGN | https://maps.app.goo.gl/VmufiMsmcASenNMp6 | | 2026-06-15 | 2027-12-15 | 2027-12-15 | 2025-01-28 | 2025-01-28 | 2025-01-31 |
221b3804-3adb-427c-bbbd-ec76e4e1f56f | Clearview Solar Project | Solar | Under Construction | Clearlight Energy Holdings | https://www.clearviewsolarproject.com/ | Private | | | | | 9560 OH-235, Quincy, OH 43343, United States | 43343 | OH | 40.26354669 | -83.97522787 | | | 144 | The Clearview Solar Project is a proposed solar generation facility located in Champaign County, Ohio, with a planned commencement of construction in 2022 1. The facility is designed to have a nameplate capacity of 144 megawatts alternating current (MWAC) 1.
The project will include ground-mounted photovoltaic (PV) modules and associated support facilities such as access roads, pyranometers, buried electrical collection lines, inverters, a facility substation, and a short transmission line ("gen-tie") that will connect the facility substation to a new utility substation 1. The total number of solar modules expected to be installed is 425,445, each with approximately 0.44 kilowatts of direct current (kWDC) capacity 1.
The project will interconnect with the Dayton Power and Light Company transmission system via a new 138 kV three-breaker ring bus switchyard that will tap the East Sidney-Quincy 138 kV line 2. The point of interconnection will be the 138 kV takeoff structure leaving the new three-breaker ring bus switchyard 2. | 20-1362-EL-BGN | https://maps.app.goo.gl/5bVjoZQer7Fhi5UJA | | 2023-06-14 | 2024-12-23 | 2025-02-28 | 2025-01-28 | 2025-01-28 | 2025-01-31 |
d74a7344-e5e7-45af-a650-2e5360706d0d | Grover Hill Wind Farm | Wind | Under Construction | Grover Hill Wind, LLC | https://groverhillwind.us/ | Private | | | | | 17372 OH-114, Grover Hill, OH 45849, USA | 45849 | OH | 41.01930963 | -84.48856092 | 9,600 | | 150 | - Location: The Grover Hill Wind Farm is located in Paulding County, Ohio 1.
- Commencement Date: The construction for the Grover Hill Wind Farm was planned for 2022 2.
- Power Output: The project has a total nameplate capacity of up to 150 megawatts (MW) and includes up to 23 turbines, each with a maximum capacity of 6 MW 2.
- Substations: The facility is proposed to interconnect from the collection substation to the AEP transmission systems at the existing Haviland 138 kV substation, which would need to be expanded to accommodate the interconnection 1.
- Data Centres: There is no mention of data centers associated with this wind energy project in the provided excerpts.
- Additional Information:
- The project was approved by the Ohio Power Siting Board, and a certificate for construction was issued 1.
- The Grover Hill Wind Farm is a major utility facility as defined by Ohio regulations 1.
- The project area was selected based on factors such as wind resource availability, access to transmission infrastructure, and community support 3.
There is no further information on the size of electrical equipment or data centers related to this or other wind energy projects in the provided excerpts. | https://dis.puc.state.oh.us/CaseRecord.aspx?CaseNo=20-417&x=12&y=12. | https://maps.app.goo.gl/p5aF3q2Z4ejkpQHFA | 2018-09-28 | 2024-11-01 | 2026-02-28 | 2026-02-28 | 2025-01-28 | 2025-01-28 | 2025-01-31 |
c79c4fa4-696a-4a44-bb07-23e22fac0d05 | Eagle Eye Solar | Solar | Announced | BrightNight LLC | https://brightnightpower.com/eagle-eye-community/ | Private | | | | | Wenden. La Paz County | 85357 | AZ | 33.901968 | -113.510276 | 3,962 | | 400 | Here is a detailed analysis of the Eagle Eye Solar Project based on the provided excerpts:
- Location: The Eagle Eye Solar Project is proposed to be situated on approximately 4,799 acres of federal land managed by the U.S. Bureau of Land Management (BLM), located about 4 miles north of Wenden in La Paz County, Arizona 1.
- Commencement Dates: Project construction is anticipated to begin as early as the third quarter of 2025, with an in-service date expected by the second quarter of 2027 1.
- Power Generation Capacity: The solar photovoltaic facility has a planned capacity of up to 400 megawatts (MW) and includes a battery energy storage system (BESS) with the same capacity 1, 1.
- Size of Electrical Equipment: The project will include a 1.2 to 2.0-mile 230-kilovolt (kV) transmission line 2, 1.
- Substations:
- The non-jurisdictional project substation will step up electricity from 34.5 kV to 230 kV. It will consist of internal power distribution systems, including buses, circuit breakers, disconnect switches, and a main step-up transformer within an 8-acre fenced enclosure 1.
- The project will interconnect at the Harcuvar substation or a new switchyard to connect to existing Western Area Power Administration (WAPA) transmission lines 2, 1.
- Data Centers: There is no mention of data centers associated with the Eagle Eye Solar Project in the provided excerpts.
- Additional Information:
- The project's transmission line is designed to minimize environmental impact and comply with various federal and state regulations, including the Endangered Species Act and the Migratory Bird Treaty Act 1, 1.
- The project will provide Arizona with a new clean, renewable energy resource, contributing to the region's renewable energy goals 1. | L-21323A-24-0209-00236 | https://maps.app.goo.gl/dCKYr4BrCK7a2N2m6 | 2024-02-07 | 2025-09-15 | | 2027-06-15 | 2025-01-28 | 2025-01-28 | 2025-01-31 |
dc213783-9242-4152-a4bf-46764dfc5687 | Eagle Eye Solar | Battery | Announced | BrightNight LLC | https://brightnightpower.com/eagle-eye-community/ | Private | | | | | Wenden. La Paz County | 85357 | AZ | 33.901968 | -113.510276 | 3,962 | | 400 | Here is a detailed analysis of the Eagle Eye Solar Project based on the provided excerpts:
- Location: The Eagle Eye Solar Project is proposed to be situated on approximately 4,799 acres of federal land managed by the U.S. Bureau of Land Management (BLM), located about 4 miles north of Wenden in La Paz County, Arizona 1.
- Commencement Dates: Project construction is anticipated to begin as early as the third quarter of 2025, with an in-service date expected by the second quarter of 2027 1.
- Power Generation Capacity: The solar photovoltaic facility has a planned capacity of up to 400 megawatts (MW) and includes a battery energy storage system (BESS) with the same capacity 1, 1.
- Size of Electrical Equipment: The project will include a 1.2 to 2.0-mile 230-kilovolt (kV) transmission line 2, 1.
- Substations:
- The non-jurisdictional project substation will step up electricity from 34.5 kV to 230 kV. It will consist of internal power distribution systems, including buses, circuit breakers, disconnect switches, and a main step-up transformer within an 8-acre fenced enclosure 1.
- The project will interconnect at the Harcuvar substation or a new switchyard to connect to existing Western Area Power Administration (WAPA) transmission lines 2, 1.
- Data Centers: There is no mention of data centers associated with the Eagle Eye Solar Project in the provided excerpts.
- Additional Information:
- The project's transmission line is designed to minimize environmental impact and comply with various federal and state regulations, including the Endangered Species Act and the Migratory Bird Treaty Act 1, 1.
- The project will provide Arizona with a new clean, renewable energy resource, contributing to the region's renewable energy goals 1. | L-21323A-24-0209-00236 | https://maps.app.goo.gl/dCKYr4BrCK7a2N2m6 | 2024-02-07 | 2025-09-15 | | 2027-06-15 | 2025-01-28 | 2025-01-28 | 2025-01-31 |
78e0ec7c-212f-4a21-b23a-e0b15ea62d57 | Hardin Solar Energy II | Solar | Active | Hardin Solar Energy LLC | https://hardinsolar.invenergy.com/ | Private | | | | | 3999-3003 Township Rd 120, Harrod, OH 45850, USA | 45850 | OH | 40.66010135 | -83.81005076 | 3297 | | 150 | Meta is buying the energy.The excerpts provide information about several solar-powered facilities in Ohio, including their locations, commencement dates, and capacities. Here is a detailed report based on the available data:
- Hardin Solar Energy II:
- Location: Hardin County, Ohio.
- Commencement of construction: June 15, 2021.
- Commercial operations date: June 30, 2023.
- Capacity: 170 MW solar photovoltaic facility.
- Equipment configuration includes a maximum facility output of 170 MW AC with the necessary additional facilities to comply with power factor requirements 1, 2.
- Hardin Solar Energy III:
- Application filed: February 12, 2021, for a 300 MW facility.
- A portion of the Hardin Solar II project area was transferred to Hardin Solar III to facilitate a 20 MW separation 3.
- Hillcrest Solar Facility:
- Location: Not specified in the excerpts.
- Operational Date: November 16, 2021 4.
These facilities are interconnected with the transmission system operated by AEP Ohio Transmission Company, Inc., and have interconnection agreements in place with PJM Interconnection, L.L.C., which manage their capacity interconnection rights 1. Specific information about associated substations, their names, sizes, and configurations is not detailed in the excerpts provided. | | | 2018-10-12 | 2019-06-15 | 2024-12-13 | 2024-12-13 | 2025-01-29 | 2025-01-29 | 2025-01-31 |
7375d2a7-9d63-4615-99d2-0a74dffdf394 | Hardin Solar Energy I | Solar | Active | Dominion Energy | https://hardinsolar.invenergy.com/ | Private | | | | | 13823 Township Rd 65, Belle Center, OH 43310, United States | 43310 | OH | 40.64465035 | -83.78344087 | 1,115 | | 150 | Meta is buying the energy. The excerpts provide information about several solar-powered facilities in Ohio, including their locations, commencement dates, and capacities. Here is a detailed report based on the available data:
- Hardin Solar Energy II:
- Location: Hardin County, Ohio.
- Commencement of construction: June 15, 2021.
- Commercial operations date: June 30, 2023.
- Capacity: 170 MW solar photovoltaic facility.
- Equipment configuration includes a maximum facility output of 170 MW AC with the necessary additional facilities to comply with power factor requirements 1, 2.
- Hardin Solar Energy III:
- Application filed: February 12, 2021, for a 300 MW facility.
- A portion of the Hardin Solar II project area was transferred to Hardin Solar III to facilitate a 20 MW separation 3.
- Hillcrest Solar Facility:
- Location: Not specified in the excerpts.
- Operational Date: November 16, 2021 4.
These facilities are interconnected with the transmission system operated by AEP Ohio Transmission Company, Inc., and have interconnection agreements in place with PJM Interconnection, L.L.C., which manage their capacity interconnection rights 1. Specific information about associated substations, their names, sizes, and configurations is not detailed in the excerpts provided. | 17-0773-EL-BGN | https://maps.app.goo.gl/J9XuL1hqJEqexniB9 | 2017-07-05 | | 2020-12-15 | 2020-06-15 | 2025-01-29 | 2025-01-29 | 2025-01-31 |
1caf3f25-38c7-4d1e-9e29-ac5fc05860d3 | Ranegras Plains Energy Center | Solar | Announced | Ranegras Plains Energy Center LLC | https://ranegrasplainsenergycenter.com/ | Private | | | | | La Paz County 25 miles east of the Town of Quartzsite | 85357 | AZ | 33.63473596 | -113.8153497 | 5,005 | | 700 | | L-21344A-24-0273-00243 | https://maps.app.goo.gl/p7NdeQU24GF2Yw639 | 2024-12-20 | 2025-12-15 | 2028-12-15 | | 2025-01-29 | 2025-01-29 | 2025-01-31 |
e6e1537e-3d33-4736-b0ee-a857da2cf34b | Ranegras Plains Energy Center | Battery | Announced | Ranegras Plains Energy Center LLC | https://ranegrasplainsenergycenter.com/ | Private | | | | | La Paz County 25 miles east of the Town of Quartzsite | 85357 | AZ | 33.63473596 | -113.8153497 | 5,005 | | 700 | | L-21344A-24-0273-00243 | https://maps.app.goo.gl/p7NdeQU24GF2Yw639 | 2024-12-20 | 2025-12-15 | 2028-12-15 | | 2025-01-29 | 2025-01-29 | 2025-01-31 |
609266c0-b626-4a73-b5be-e2cb69f68bab | Atlanta Farms Solar Project | Solar | Active | Atlanta Farms Solar Project LLC | https://savionenergy.com/ | Private | | | | | 26440 State Rte 207, New Holland, OH 43145, United States | 43145 | OH | 39.55798349 | -83.17813596 | 1375 | | 199.6 | The Atlanta Farms Solar Project is a solar-powered facility developed by Atlanta Farms Solar Project, LLC, a private entity. The project is located in Deer Creek and Perry Townships, Pickaway County, Ohio, and will occupy up to 1,375 acres within a 2,276-acre project area 1. It is designed to generate 199.6 megawatts of energy 1.
Key dates for the project include:
- Application filed: January 31, 2020 1.
- Construction start date: Planned for the third quarter of 2021 2.
- Expected commercial operation date: End of 2022 2.
The project includes significant electrical equipment and infrastructure:
- Approximately 25 miles of underground AC collection lines and 10 miles of underground DC collection lines 3.
- Four separate substations will occupy approximately three acres collectively, with a configuration involving collection line feeders, breakers, a 69 kV bus, and main power transformers to step up voltage to 69 kV 4.
- The facility would utilize approximately 635,000 to 676,000 solar modules and 80 inverters 4.
- The collector system will include up to 35 miles of buried cable 4.
There are no mentions of data centers or additional facilities such as those specifically dedicated to data processing within the provided excerpts. | 19-1880-EL-BGN | https://maps.app.goo.gl/26ZNKFqhuZAHFP9y9 | 2020-01-31 | 2022-08-15 | 2023-12-15 | 2023-12-15 | 2025-01-29 | 2025-01-29 | 2025-01-31 |