d73f5a70-3f46-11f1-ab20-755aac1bed81 | Amkor Peoria Fab Facility - Phase 2 | | | Amkor Technology Inc. | AMKR | NVIDIA, Apple | Construction | 33.799759 | -112.275616 | 10000 Old Carefree Hwy, Peoria, AZ 85383, USA | 85383 | Maricopa County | 04013 | Peoria | AZ | 7000000000 | 104 | 750000 | 2025-10-06 | | 2025-10-01 | 2026-05-31 | 0.5 | 2028-12-31 | 2028-12-31 | 2028-12-31 | Medium | https://www.azcommerce.com/news-events/news/2023/11/amkor-announces-us-advanced-packaging-and-test-facility-in-peoria/,https://www.azcommerce.com/news-events/news/2025/10/amkor-technology-breaks-ground-on-new-semiconductor-advanced-packaging-and-test-campus-in-peoria-expands-investment-to-7-billion/,https://www.ic-pcb.com/amkors-2b-semiconductor-facility-in-peoria-faces-backlash-from-local-residents---ic-manufacturing.html,https://www.towardspackaging.com/news/amkor-arizona-packaging-facility-peoria,https://www.manufacturingdive.com/news/amkor-to-construct-2-billion-semiconductor-packaging-and-test-facility-in-Peoria-arizona/701268/,https://www.semiconductor-digest.com/amkor-announces-new-site-for-u-s-semiconductor-advanced-packaging-and-test-facility/ | https://peoriaaz.novusagenda.com/agendapublic/CoverSheet.aspx?ItemID=8359&MeetingID=1327 | | https://maps.app.goo.gl/x7Gxec6JYJLuNH6o8 | | [2026-04-22 FC] Roof installation on Phase 2 of project appears roughly completed. Additional Info: Second record created to reflect Phase 2; Amkor Peoria Facility renamed to Amkor Peoria Facility - Phase 1 | 2026-04-23 | 2026-06-03 | 2026-06-22 |
3ee166e0-a0a6-11f0-8b90-711624bae265 | Amkor Peoria Fab Facility - Phase 1 | | | Amkor Technology Inc. | AMKR | NVIDIA, Apple | Construction | 33.799759 | -112.275616 | 10000 Old Carefree Hwy, Peoria, AZ 85383, USA | 85383 | Maricopa County | 04013 | Peoria | AZ | 7000000000 | 104 | 750000 | 2023-12-01 | | 2025-08-15 | 2026-05-31 | 0.5 | 2028-03-01 | 2028-03-01 | 2028-03-01 | Medium | https://www.azcommerce.com/news-events/news/2023/11/amkor-announces-us-advanced-packaging-and-test-facility-in-peoria/,https://www.azcommerce.com/news-events/news/2025/10/amkor-technology-breaks-ground-on-new-semiconductor-advanced-packaging-and-test-campus-in-peoria-expands-investment-to-7-billion/,https://www.ic-pcb.com/amkors-2b-semiconductor-facility-in-peoria-faces-backlash-from-local-residents---ic-manufacturing.html,https://www.towardspackaging.com/news/amkor-arizona-packaging-facility-peoria,https://www.manufacturingdive.com/news/amkor-to-construct-2-billion-semiconductor-packaging-and-test-facility-in-Peoria-arizona/701268/,https://www.semiconductor-digest.com/amkor-announces-new-site-for-u-s-semiconductor-advanced-packaging-and-test-facility/ | https://peoriaaz.novusagenda.com/agendapublic/CoverSheet.aspx?ItemID=8359&MeetingID=1327 | | https://maps.app.goo.gl/x7Gxec6JYJLuNH6o8 | https://www.peoriaaz.gov/Home/Components/News/News/6822/439 | [2025-10-03 DS] Construction: Site clearing underway. Additional Info: Site to be operational in early 2028.
[2025-10-07 DS] Additional Info: Amkor has announced an additional $5b investment for this project, raising the total to $7b.
[2026-04-23 FC] Roof installation appears completed. Additional Info: Renamed to Amkor Peoria Facility - Phase 1, Phase 2 -> Amkor Peoria Facility - Phase 2 | 2025-10-03 | 2026-06-03 | 2026-06-22 |
204b52b0-c0bb-11f0-a412-91545074890b | Samsung Taylor Fab - 1 | eff8d308-9905-4fc2-b5dd-b701941a0157 | Samsung Taylor Fab Campus | Samsung Electronics | 005930.KS | HDR, Applied Materials, Linde, Yates Construction | Construction | 30.537495 | -97.454407 | GGPW+X6 Taylor, TX, USA | 76574 | Williamson County | 48491 | Taylor | TX | 37000000000 | 1200 | 6000000 | 2021-11-23 | | 2022-03-01 | 2026-05-24 | 0.95 | 2026-12-01 | 2026-12-01 | 2026-12-01 | High | https://semiconductor.samsung.com/sas/company/taylor/,https://kr.usembassy.gov/041524-biden-harris-administration-announces-preliminary-terms-with-samsung-electronicsto-establish-leading-edge-semiconductor-ecosystem-in-central-texas/,https://www.semiconductor-digest.com/samsung-electronics-to-establish-leading-edge-semiconductor-ecosystem-in-central-texas-with-chips-act-funding/,https://www.trendforce.com/news/2026/03/25/news-samsung-reportedly-to-build-a-new-wafer-fab-in-the-u-s/, https://services.austintexas.gov/edims/document.cfm?id=309893 | | | https://maps.app.goo.gl/7xwgrvdMPH6RxqSBA | | [2026-04-01 FC] Site cleared and land graded adjacent to Fab 1, potentially for Fab 2; site clearing underway on southern and western side, and foundational construction underway on southwest side. Additional Info: Fab 1 is expected to begin mass production in 2027. Fab 2 still under regulatory review.
[2026-05-11 FC] No construction progress per latest satellite image from 2026-05-10.
[2026-05-14 FC] Construction: Shell and exterior work remain complete with no visible changes as of latest satellite image. Close to activation; Additional Info: Updated construction to 95% based on proximity to activation status. | 2025-11-13 | 2026-06-02 | 2026-06-22 |
3cb61a60-31cd-11f1-9859-476a8ab369c6 | Samsung Taylor Fab - 2 | eff8d308-9905-4fc2-b5dd-b701941a0157 | Samsung Taylor Fab Campus | Samsung Electronics | 005930.KS | HDR, Applied Materials, Linde, Yates Construction | Announcement | 30.541468 | -97.451972 | GGPW+X6 Taylor, TX, USA | | | | Taylor | TX | 37000000000 | | | 2024-04-15 | | | 2026-05-24 | 0 | | | | Medium | https://semiconductor.samsung.com/sas/company/taylor/,https://kr.usembassy.gov/041524-biden-harris-administration-announces-preliminary-terms-with-samsung-electronicsto-establish-leading-edge-semiconductor-ecosystem-in-central-texas/,https://www.semiconductor-digest.com/samsung-electronics-to-establish-leading-edge-semiconductor-ecosystem-in-central-texas-with-chips-act-funding/,https://www.trendforce.com/news/2026/03/25/news-samsung-reportedly-to-build-a-new-wafer-fab-in-the-u-s/, https://services.austintexas.gov/edims/document.cfm?id=309893, https://koreajoongangdaily.joins.com/news/2026-03-17/business/industry/Samsung-moves-toward-second-chip-factory-in-Taylor-as-demand-surges/2543455 | https://taylortx.new.swagit.com/videos/376553 | | | | [2026-04-01 FC] Site cleared and land graded adjacent to Fab 1, potentially for Fab 2; site clearing underway on southern and western side, and foundational construction underway on southwest side. Additional Info: HDR Engineering behind this project (as per Taylor City Council Meeting 2026-02-26) and was approved for an expedited permitting process for Fab 2.
[2026-05-11 FC] Site clearing underway
[2026-05-14 FC] Additional Info: Site has remained cleared although Fab 2 is still in regulatory review. | 2026-04-06 | 2026-06-02 | 2026-06-22 |
cde7f9b0-27b2-11f1-97b4-0b16f14adc33 | Tesla SpaceX TeraFab | | | Tesla, Intel Corporation, SpaceX, xAI | TSLA, INTC | | Announcement | 30.622432 | -96.010578 | JXCQ+XQ Singleton, TX, USA | 77831 | Grimes County | 48185 | Singleton | TX | 119000000000 | | 100000000 | 2026-02-21 | | | 2026-06-09 | 0 | | | | Medium | https://x.com/Tesla/status/2035526423495180779,https://www.independent.co.uk/bulletin/news/elon-musk-terafab-tesla-spacex-b2943803.html,https://x.com/intel/status/2041501301318766866?s=20,https://techcrunch.com/2026/04/07/intel-signs-on-to-elon-musks-terafab-chips-project/,https://www.kbtx.com/2026/05/13/terafab-could-transform-grimes-countys-economy-experts-say/,https://terafab.ai/,https://www.kbtx.com/2026/06/03/grimes-county-approves-reinvestment-zone-massive-spacex-project-still-considering-tax-breaks/,https://www.tomshardware.com/tech-industry/big-tech/elon-musks-spacex-secures-100-percent-property-tax-exemption-for-planned-usd55-billion-terafab-semiconductor-factory-in-texas-county-approves-35-year-deal-worth-hundreds-of-millions-despite-resident-backlash | https://grimescountytexas.gov/vertical/sites/%7B958238D0-27E6-4F6C-919E-F1D98542C5FD%7D/uploads/SpaceX_-_Grimes_County_-_30_Day_Notice_of_Tax_Abatement_(proposed_for_posting_by_May_4_for_June_3_meeting).pdf,https://grimescotx.portal.civicclerk.com/event/1272/files/agenda/4461,https://grimescotx.portal.civicclerk.com/event/1266/files/agenda/4457 | | https://maps.app.goo.gl/UB4WVJbFdfTvA4qR9 | | [2026-03-24 FC] Additional Info: Exact location undisclosed; several sites being assessed. Advanced Technology Fab possibly to be built on GigaTexas, the Texas Gigafactory; this will serve for experimentation and improvement.
[2026-04-08 FC] Additional Info: Intel to partner in this project
[2026-05-14 FC] Additional Info: Filing to discuss tax abatement approval for site on Gibbons Creek Reservoir, Grimes County, Texas. Meeting to be held 2026-06-03. Mentions total investment potentially $119bn.
[2026-05-19 FC] Additional Info: Added official website to datasheet URLs.
[2026-06-03 FC] Additional Info: Grimes County commissioners approved reinvestment zone for Terafab project. Tax breaks still in discussion. Tesla will use Intel's 14A production process in this project.
[2026-06-04 FC] Additional Info: Grimes County commissioners approved 100% tax abatement over a 35 year PILOT. Approxmiate location visible from reinvestment zoning application.
[2026-06-10 FC] Construction: No site clearing activity visible | 2026-03-24 | 2026-06-10 | 2026-06-22 |
bcccdad0-4268-11f1-a4a7-671c4015c6fd | AOI Blue Ridge Commerce Center Fab 3 | | | AOI | AAOI | | Announcement | 29.585999 | -95.509225 | HFPR+98 Fort Bend Houston, Houston, TX, USA | | | | Houston | TX | | | 153928 | 2026-02-10 | | | 2026-05-31 | 0 | 2027-12-31 | 2027-12-31 | 2027-12-31 | Medium | https://www.investing.com/news/sec-filings/applied-optoelectronics-signs-130month-lease-for-houston-facility-with-purchase-option-93CH-4532802,https://traded.co/deals/texas/industrial/lease/16851-blue-ridge-commerce-dr/ | https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026016172 | | https://maps.app.goo.gl/dQt8dpbS3VX6gZgd6 | | [2026-04-27 FC] Additional Info: This is going to be a retrofit | 2026-04-27 | 2026-06-03 | 2026-06-22 |
c5468e40-2ee5-11f1-b6e2-8b6f880046be | Intel Ohio One Fab Campus - Mod 2 | 51691fd8-1ee2-426f-af59-57a2fae65664 | Intel Ohio One Fab Campus | Intel Corporation | INTC | Bechtel Corporation, Gilbane Building, Mcdaniels Construction Corp., INC., Northstar Contracting, Barnhart Crane & Rigging, CTL Engineering, Inc., Currie & Brown, EMH&T, Geotechnical Consultants, Inc., Lithko Contracting, SSOE Group, Linde Engineering | Construction | 40.117145 | -82.710221 | 11805 Green Chapel Rd NW, Johnstown, OH 43031, USA | 43031 | Licking County | 39089 | Johnstown | OH | 28000000000 | 1000 | | 2022-01-21 | | 2022-08-01 | 2026-05-30 | 0.4 | 2031-01-01 | 2031-01-01 | 2031-01-01 | High | https://newsroom.intel.com/corporate/ohio-one-construction-timeline-update, https://www.bechtel.com/press-releases/bechtel-to-build-intels-semiconductor-manufacturing-facilities-in-ohio/, https://columbusconstruction.org/intel-taps-bechtel-as-gc-for-new-albany-project/, https://www.intc.com/news-events/press-releases/detail/1549/intel-selects-diverse-ohio-based-team-to-lead-early | https://siliconheartland.newalbanyohio.org/permits/, https://edocpub.epa.ohio.gov/publicportal/ViewDocument.aspx?docid=2046410 | | https://maps.app.goo.gl/YTSDAga9hFCnoBh67 | | [2025-10-08 DS] Construction: Site work active but has been intentionally slowed down according to Intel. Basement level of the plant is complete and work on the above-ground structure is now underway; Additional Info: Plans for 2 plants. First plant is expected to be completed in 2030 and go live in 2031, second plant is expected to be compelted in 2031 and go live in 2032 (a delay of at least five years from the original timeline).
[2026-04-01 FC] Vertical construction largely completed for plant 2 (mod 2). Roof being installed on northeastern section progressing southwest. Additional Info: Bechtel Corporation handling construction for this project, for all phases. There are likely to be 4 phases each with 2 fabs.
[2026-04-15 FC] Additional Info: Updated construction companies
[2026-05-11 FC] No new construction progress per latest satellite photo from 2026-04-25
[2026-05-14 FC] Construction: Shell almost completed with only southwest portion of roof remaining to be installed. Cooling equipment to west of building still to be installed. | 2026-04-02 | 2026-06-01 | 2026-06-22 |
a11ad750-a45d-11f0-a2a1-0755b242f3d0 | Intel Ohio One Fab Campus - Mod 1 | 51691fd8-1ee2-426f-af59-57a2fae65664 | Intel Ohio One Fab Campus | Intel Corporation | INTC | Bechtel Corporation, Gilbane Building, Mcdaniels Construction Corp., INC., Northstar Contracting, Barnhart Crane & Rigging, CTL Engineering, Inc., Currie & Brown, EMH&T, Geotechnical Consultants, Inc., Lithko Contracting, SSOE Group, Linde Engineering | Construction | 40.118964 | -82.709205 | 11805 Green Chapel Rd NW, Johnstown, OH 43031, USA | 43031 | Licking County | 39089 | Johnstown | OH | 28000000000 | 1000 | | 2022-01-21 | | 2022-08-01 | 2026-05-30 | 0.6 | 2030-01-01 | 2030-01-01 | 2030-01-01 | High | https://newsroom.intel.com/corporate/ohio-one-construction-timeline-update, https://www.bechtel.com/press-releases/bechtel-to-build-intels-semiconductor-manufacturing-facilities-in-ohio/, https://columbusconstruction.org/intel-taps-bechtel-as-gc-for-new-albany-project/, https://www.intc.com/news-events/press-releases/detail/1549/intel-selects-diverse-ohio-based-team-to-lead-early | https://siliconheartland.newalbanyohio.org/permits/, https://edocpub.epa.ohio.gov/publicportal/ViewDocument.aspx?docid=2046410 | | https://maps.app.goo.gl/aekgXipTiswAVvz26 | https://newsroom.intel.com/press-kit/intel-invests-ohio | [2025-10-08 DS] Construction: Site work active but has been intentionally slowed down according to Intel. Basement level of the plant is complete and work on the above-ground structure is now underway; Additional Info: Plans for 2 plants. First plant is expected to be completed in 2030 and go live in 2031, second plant is expected to be compelted in 2031 and go live in 2032 (a delay of at least five years from the original timeline).
[2026-04-01 FC] Shell construction of plant 1 (mod 1) complete, roof installed. Additional Info: Bechtel Corporation handling construction for this project, for all phases. There are likely to be 4 phases each with 2 fabs.
[2026-04-15 FC] Additional Info: Updated construction companies
[2026-05-11 FC] No new construction progress per latest satellite photo from 2026-04-25
[2026-05-14 FC] Construction: Shell remains completed with no new construction work visible on main building. | 2025-10-08 | 2026-06-01 | 2026-06-22 |
00db2820-daaf-11f0-9bba-771384578343 | Micron Clay Fab Campus - Fab 1 | c68ce999-2e1b-405d-9add-87dc775ae116 | Micron Clay Fab Campus | Micron Technology | MU | WSP, Gilbane Building, Bechtel Corporation | Construction | 43.191695 | -76.162707 | 8798 Caughdenoy Rd, Clay, NY 13041, USA | 13041 | Onondaga County | 36067 | Clay | NY | 100000000000 | 1400 | 1200000 | 2022-10-07 | | 2026-02-15 | 2026-06-13 | 0.05 | 2030-09-30 | 2030-09-30 | 2033-09-30 | High | https://www.syracuse.com/business/2022/10/micron-picks-syracuse-suburb-for-huge-computer-chip-plant-that-would-bring-up-to-9000-jobs.html
https://evertiq.com/design/2026-01-08-micron-to-break-ground-on-new-york-megafab
https://www.nist.gov/chips/micron-new-york-clay
https://townofclayny.gov/sites/default/files/2025-10/Micron%20New%20York%20Planning%20Board%20Presentation_10.08.2025_FINAL.pdf
https://dec.ny.gov/sites/default/files/2025-12/micronnysemiconductor.pdf
https://assets.micron.com/adobe/assets/urn:aaid:aem:60a75ad5-0759-47bc-beb6-b3fe5de0114f/renditions/original/as/clcpa-analysis-combined.pdf
https://ongoved.com/wp-content/uploads/2025/06/Micron-Draft-EIS.pdf
https://townofclayny.gov/sites/default/files/2025-10/Micron%20New%20York%20Planning%20Board%20Presentation%2010-22-2025.pdf,https://constructionreviewonline.com/bechtel-selected-for-first-phase-of-microns-new-york-semiconductor-complex/,https://investors.micron.com/news-releases/news-release-details/micron-selects-bechtel-construction-partner-historic-new-york | | | https://maps.app.goo.gl/v3BNrVP3mP32rVsP8 | | [2025-12-16 DS] Additional Info: Campus will have a total of 4 fabs. Current timeline provided by Micron shows that Fab 1 would be active in Q3 2030, Fab 2 in Q4 2033, Fab 3 in Q3 2037, and Fab 4 by Q4 2041. Construction for Fab 1 is expected to start in 2026.
[2026-04-06 FC] Site clearing underway, possibly covering Fab 1 and 2. Additional Info: Updated datasheet URL with site plan and environmental assessment.
[2026-05-11 FC] No new construction per latest satellite image from 2026-05-04
[2026-05-13 FC] Construction: No new site clearing or construction activity to update construction percentage based on latest satellite imagery. Site being cleared for Phase 1 according to board presentation. Area includes large portion to east of Fab 1 for temporary parking and auxiliary work; Additional Info: Updated project stage from Announcement to Construction. Construction start date estimated from progress between 2026-01-20 and 2026-03-09. Construction finished date updated from 2030-09-30.
[2026-06-16 FC] Additional Info: Added Bechtel as a construction company based on EPC award announcement. | 2025-12-16 | 2026-06-16 | 2026-06-22 |
c5c86ba0-2ee9-11f1-b6e2-8b6f880046be | Micron Clay Fab Campus - Fab 2 | c68ce999-2e1b-405d-9add-87dc775ae116 | Micron Clay Fab Campus | Micron Technology | MU | WSP, Gilbane Building, Bechtel Corporation | Announcement | 43.191312 | -76.156893 | 5RRV+86 Clay, NY, USA | 13041 | Onondaga County | 36067 | Clay | NY | 100000000000 | | 1200000 | 2022-10-07 | | | 2026-06-13 | 0 | 2033-09-30 | 2033-09-30 | 2035-09-30 | High | https://www.syracuse.com/business/2022/10/micron-picks-syracuse-suburb-for-huge-computer-chip-plant-that-would-bring-up-to-9000-jobs.html
https://evertiq.com/design/2026-01-08-micron-to-break-ground-on-new-york-megafab
https://townofclayny.gov/sites/default/files/2025-10/Micron%20New%20York%20Planning%20Board%20Presentation_10.08.2025_FINAL.pdf
https://www.nist.gov/chips/micron-new-york-clay
https://dec.ny.gov/sites/default/files/2025-12/micronnysemiconductor.pdf
https://assets.micron.com/adobe/assets/urn:aaid:aem:60a75ad5-0759-47bc-beb6-b3fe5de0114f/renditions/original/as/clcpa-analysis-combined.pdf
https://ongoved.com/wp-content/uploads/2025/06/Micron-Draft-EIS.pdf,https://constructionreviewonline.com/bechtel-selected-for-first-phase-of-microns-new-york-semiconductor-complex/,https://investors.micron.com/news-releases/news-release-details/micron-selects-bechtel-construction-partner-historic-new-york | | | https://maps.app.goo.gl/v3BNrVP3mP32rVsP8 | | [2025-12-16 DS] Additional Info: Campus will have a total of 4 fabs. Current timeline provided by Micron shows that Fab 1 would be active in Q3 2030, Fab 2 in Q4 2033, Fab 3 in Q3 2037, and Fab 4 by Q4 2041. Construction for Fab 1 is expected to start in 2026.
[2026-04-06 FC] Site clearing underway, possibly covering Fab 1 and 2. Additional Info: Updated datasheet URL with site plan and environmental assessment.
[2026-05-11 FC] No new construction per latest satellite image from 2026-05-04
[2026-05-13 FC] Construction: No new site clearing or construction activity to update construction percentage based on latest satellite imagery. Site being cleared for Phase 1 according to board presentation. Area includes large portion to east of Fab 1 for temporary parking and auxiliary work; Additional Info: Construction finished date updated from 2030-09-30.
[2026-06-16 FC] Additional Info: Added Bechtel as a construction company based on EPC award announcement. | 2026-04-02 | 2026-06-16 | 2026-06-22 |